Thursday, April 21, 2011
Barnhart Powers Forward in Transformer Transport
Tuesday, April 12, 2011
Transport and Setting of Turbine/Generator in a North Carolina Project
Market: Power
Location: North Carolina

The Challenge
Barnhart Crane & Rigging Co. won a bid on an already-in-progress job, which included the hauling, lifting, and setting of steam equipment, and the customer urged the team to finish the job on a very tight schedule. On top of that, very wet and extremely cold weather made the project even more difficult, not to mention a very constricting site gave the crew very little real-estate in which to work.

The Solution
Creative planning, hard work, and timely deliveries all helped Barnhart meet the deadline. In addition, clever engineering enabled the team to connect the Marino girder to the Barnhart gantry track, and as a result, saved much time and money.
The Description
The customer contracted Barnhart for the onsite transporting and setting of the turbine in addition to a generator. The job required the team to lift, haul, and set these massive pieces to an alternative location on the job site.
The project was already underway when the crew won the bid, and the customer desired a quick finish. Barnhart engineers then focused on quickly submitting the project plans. Other engineers on the site also flooded the team's engineers with questions, and Barnhart's quick responses kept the job on schedule.
Barnhart's engineers also developed a plan to connect the Marino girders with the Barnhart gantry tracks. This allowed the team more flexibility and availability with its equipment and saved quite a bit of time and money.

The rest of the crew suffered through cold and wet weather. In fact, the site conditions heavily constricted the equipment because of minimal space to navigate machinery. The crane operators and workers pressed onward with hard work and overcame the dreary setting.
A subcontractor also delivered integral parts and equipment to Barnhart right on schedule. This timely delivery, matched with Barnhart's creative engineering staff and diligent crew, allowed Barnhart to start a job behind schedule and finish ahead of the deadline.
Major Equipment Used
- Goldhofer Trailer
- Stator Frame
- 500T Hoist
Barnhart Crane & Rigging Company Services:
- Crane Service
- Heavy Rigging
- Heavy Cargo Logistics
- Heavy Lift Cranes
- Machinery Moving
- Modular Lift Tower
- Transportation Solutions
Monday, April 4, 2011
Despite Difficult Hurdles, Barnhart Races to Quick Finish in Generator Heavy Haul
Market: Power
Location: Tennessee

The Challenge
A customer called on Barnhart Crane & Rigging Co. in the "11th hour" for a heavy haul job, including the transportation of three combustion turbines and three combustion generators. One of the most difficult routes a Barnhart team has ever maneuvered and the need for a quick permit obtainment called for a perfect performance by the company.
The Solution
Barnhart quickly secured the required permits from the State of Tennessee for this difficult job. After quickly obtaining the permits, Barnhart won the job for the original bid value, but that only allowed them to leap the first hurdle in this job.
Next, Barnhart's careful planning, ingenuity, and friendly negotiations helped them save time, secure their routes, make tight turns, and safely navigate steep hills and narrow roadways.
In fact, Barnhart conducted numerous pre-mobilization and operation meetings, in addition to daily job hazard analyses, to successfully complete the job.

The Description
After being called in late by the customer, Barnhart won the bid on the heavy haul job because they quickly secured the required permits while the competitor failed to do so. Friendly relations with the state and a commitment to safety and government guidelines quickly allowed the team to obtain the permits.
The original schedule for the job called for a delivery every ten days. However, the team compressed the schedule to one delivery every seven days to ensure timely completion. This seems even more impressive when one considers the team covered a 74-mile haul route and two cities during every delivery.
The crew faced its first obstacle with a faulty railroad crossing. A careful inspection led to an engineering effort to shore up the bridge, ensuring a safe crossing.
Next, Barnhart negotiated terms with a do-it-yourself car wash because the car wash blocked Barnhart's route on a tight turn. The car wash agreed to demolish the building, and the trailers safely maneuvered the turn. In fact, the road on which the car wash sat was perhaps the tightest road Barnhart has ever had to squeeze through!
The last part of the route included a five percent grade and a road width of nineteen feet. The dolly transport itself stretched just under eighteen feet wide! After numerous meetings and careful transport, the team safely completed the job.
Barnhart's hard work and careful planning ultimately led to an extraordinary achievement with this job. Despite the tight schedule and daunting obstacles, the team managed a near perfect performance!
Major Equipment Used
- 16- and 20- Line Dolly Transporters
Barnhart Crane & Rigging Company Services:
- Crane Service
- Heavy Rigging
- Heavy Cargo Logistics
- Heavy Lift Cranes
- Machinery Moving
- Modular Lift Tower
- Transportation Solutions